Small Arms Inspection Building – Summer/Fall 2024 Roof Construction Update

By July 26, 2024Events, Ward 1

Pre-construction for the SAIB reroofing and associated siteworks is underway including, material orders/fabrication and site mobilization.

Over the next few months site activities will include:

  • Site hoarding at rear parking area;
  • Minor grading at the West lawn to create a temporary swale;
  • Interior roof drain installation; and,
  • Re-roofing work.

The building will remain closed to the public during the construction activities for health and safety reasons and will re-open in October.

The drive aisle and east parking lot will remain open during construction activities for public use.

Exterior hose bids for the community garden will also remain in use during construction.