Lakefront Promenade boardwalk construction update

By August 24, 2020Events, Issues, Resources
  • Construction of Area 9 boardwalk has resumed. Area 9 is located at Douglas Kennedy Headland by the spray pad and playground –see below. Completion of the boardwalk is anticipated end of October, pending steady flow of wood supply.
  • Construction of Area 1 boardwalk is still on hold. Area 1 is by the large parking lot at A.E. Crookes parking lot – see below. Supply of wood decking is anticipated within 3 weeks. Completion of Area 1 would take approximately  6 weeks once the contractor mobilizes.  I will keep you updated of any new developments.

Please let me know if you have any questions.