Hazel McCallion Line Construction Updates

By July 19, 2023August 15th, 2023Hurontario LRT, Ward 1

Mississauga South

Work is progressing along Hurontario in Misssisauga! Keep up to date with what is happening and where:

Stormwater Relocation Work – New
Watermain connections between LSW and Mineola Road – Ongoing
Traffic Staging Southbound Lanes – Ongoing
Utility Relocations & Roadworks Mississauga South – Ongoing

Progress on the Hazel McCallion Line
Port Credit residents will see significant progress on the construction of the Hazel McCallion Line around their neighbourhood’s GO station:

Mary Fix Creek has been undergoing a transformative revitalization as part of the Hazel McCallion Line project and is nearing completion.

Work crews are reconstructing 400 metres of the creek bed, which is vital to preventing floods and erosion. To date, around 325 metres are complete, with the remainder expected to be finished this year.

Read more about the Mary Fix Creek revitalization and updates to Port Credit GO at metrolinx.com

To get updates and stay informed, please subscribe now.