New Water Service Connections to all Properties between the Lakeshore West Rail Bridge to Mineola Road – June 29, 2023 to July 29, 2023 from 7 a.m. to 10 p.m. with some overnight works

By Hurontario LRT, Resources, Ward 1

What work is taking place?

As utility upgrades progress in the area, crews will be connecting properties along Hurontario Street, between the GO Lakeshore West rail bridge and Mineola Road, to the new watermain infrastructure that has recently been installed along the road alignment. The work is expected to take place as early as June 29 and will last approximately one month to July 29. Crews will be working Monday to Saturday, from 7 a.m. to 10 p.m. In some instances, overnight work will be required at the direction of the Region of Peel for temporary water service disruptions during the connections.

All the connection points are within the municipal right of way. Most of the connection points are located within the municipal side of existing driveways or the public boulevard. To make these connections, crews will need to excavate a small area up to the property line. As a result, there may be temporary impacts to water service, driveway access, and lawns/trees/hedging that are in direct conflict with the connection points. All impacted driveways will be temporarily restored using hot mix asphalt until permanent restoration takes place with final grading and re-surfacing. Any disruption to lawns/trees/ hedging will be reinstated during the final landscaping phase of the project. Individual property owners/managers directly impacted will be notified by the Region of Peel in advance of the impacts specific to their water service connection.

In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, loaders, and other construction equipment related to this work.

All works will be carried out in accordance with the Ontario Municipalities Act for the purposes of providing a water public utility with respect to accessing private property as needed. For more information on this Act please visit the government of Ontario webpage on public utilities at https://www.ontario.ca/laws/statute/01m25#BK89

Please note, work may be rescheduled due to inclement weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.

TIMING

• Work is expected to begin as early as June 29, 2023, to July 29, 2023

• Working hours are Monday to Saturday, from 7 a.m. to 10 p.m. Some overnight works will be required at the direction of the Region of Peel.

• Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.

TRAFFIC DETAILS

• Watch for slow moving vehicles entering and exiting work areas.

• Remember to reduce your speed when approaching lane reductions.

WHAT TO EXPECT?

• Every effort will be made to minimize disruptions.

• There may be temporary impacts to water service, driveway access, lawns/trees/hedging that are in direct conflict with the connection points.

• Individual property owners/manager directly impacted will be notified by the Region of Peel in advance of the impacts specific to their water service connection.

• Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, triaxles, backhoes, and other construction equipment related to this work.

TRANSIT DETAILS

• MiWay will continue to operate with regular service.

• Watch for additional signs directing passengers at bus stops as boarding areas may be relocated. Visit www.miway.ca/updates for updates on your route.

PEDESTRIAN DETAILS

• Please take care when travelling near construction areas.

• Sidewalk access in the area could be affected.

• Watch for additional signs directing pedestrians as detours may be required to ensure pedestrian safety.

CONTACT US

• Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project.

• 24-hour line 416-202-7500

Contact Us:
Call us: 416-202-7500
Write to us at: peel@metrolinx.com
Find us on Twitter @HurontarioLRT
Visit the website and sign up for our newsletter: www.metrolinx.com/hurontariolrt

Notice of Bus Stop Impact: #0331 – SB Hurontario St at Indian Valley Trail | Wednesday, June 14, 2023

By Hurontario LRT, Resources

Please be advised of the following stop impacts. See the related details below:

Stop(s) Impacted:  No.: 0331: SB Hurontario St at Indian Valley Trail

Temporary Stop Location:

0305 – Hurontario St South Of Indian Valley Trail (195m south)

0329 – Hurontario St at Pinetree Way (315m north)

Routes Impacted: 2 South

Date and Time: Wednesday, June 14, 2023 @ 7:00am

Estimated Duration: until Thursday, June 22, 2023 @ 7:00am

Event Type: HuLRT

Agency: Mobilinx

Notes:

–             Stops will remain accessible;

–             No detours required.

Should there be any questions/concerns, please contact: MiWay.Infrastructure@mississauga.ca.

Notice of Bus Stop Impact: #0333 – SB Hurontario St at Mineola Rd W | Wednesday, May 31, 2023

By Hurontario LRT

Stop Impacted:  No.: 0333: SB Hurontario St at Mineola Rd W

Temporary Stop Location: North of the intersection

Routes Impacted: 2 South

Date and Time: Wednesday, May 31, 2023 @ 7:00am

Estimated Duration: Until Friday, June 9, 2023 @ 7:00am

Event Type: HuLRT

Agency: Mobilinx

Notes:

–             Stops will remain accessible;

–             No detours required.

Any questions or concerns, please contact: MiWay.Infrastructure@mississauga.ca.

Temporary Road Closure of Mineola Road West and East – West Closure: Saturday June 3, 2023. East Closure: Sunday June 4, 2023.

By Hurontario LRT, Ward 1

The LRT contractor is installing water utilities at the intersection of Mineola Road West/Mineola Road East and Hurontario Street.  The works will be done in stages as follows:

Mineola Road West Closure at Hurontario Street:

  • On Saturday June 3rd, Mineola Road West at Hurontario Street will be closed with a local detour provided for residents to access Mineola Road West using Indian Valley Trail and Glenburnie Road.  Works will occur between 7 am and 10 pm
  • During the closure, motorists (including Emergency Services) will not be able to travel west on Mineola Road West or to access Hurontario Street from Mineola Road West on Saturday June 3rd, 2023.
  • Pedestrian access will be maintained on Mineola Road West but motorists will be required to detour to/from the area using Indian Valley Trail and Glenburnie Road

Mineola Road East Closure at Hurontario Street:

  • On Sunday June 4th, Mineola Road East at Hurontario Street will be closed with a local detour provided for residents to access Mineola Road East using Pinewood Trail and Goldthorpe Road
  • During the closure, motorists (including Emergency Services) will not be able to travel east on Mineola Road East or to access Hurontario Street from Mineola Road East on Sunday June 4th, 2023.
  • Pedestrian access will be maintained on Mineola Road East but motorists will be required to detour to/from the area using Goldthorpe Road and Pinewood Trail.

Traffic flow will be maintained along Hurontario Street at all times.

Variable Message Signs have been installed advising motorists of the planned closures and a public notice has been delivered to the area advising of the upcoming temporary road closure (below).

Please note that the LRT constructor has been approved to work between 7 am and 10 pm on Saturday and Sunday June 3 and 4th, to reduce the overall duration of the Mineola Road West and East closures.

 

What work is taking place?

As utility upgrades progress in the area, crews will be connecting the newly installed watermain infrastructure along the west and east side of Hurontario Street at Mineola Road. The working hours will take place on Saturday June 3 and Sunday June 4 from 7 a.m. to 10 p.m. This work will occur in two phases. The first phase will involve the full closure of Mineola Road on the west side of Hurontario Street to complete the new watermain connection there. The second phase will involve the full closure of Mineola Road on the east side of Hurontario Street, once the west side reopens, to complete the new watermain connection there. Work is being scheduled at this time to minimize traffic and overnight noise impacts to nearby residents.

In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, loaders, and other construction equipment related to this work.

Please note, work may be rescheduled due to inclement weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.

TIMING

• Work is scheduled on the west side of Hurontario Street at Mineola Road West for Saturday June 3, 2023, from 7 am to 10 pm.

• Work is scheduled on the east side of Hurontario Street at Mineola Road East for Saturday June 4, 2023, from 7 am to 10 pm.

• Both sides of Mineola Road will not be closed at the same time

• Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.

TRAFFIC DETAILS

• Temporary lane reductions will be required on Hurontario Street.

• Access to Mineola Road West from Hurontario Street will be available from Indian Valley Trail and Glenburnie Road.

• Access to Mineola Road East from Hurontario Street will be available from Pinewood Trail and Goldthorpe Road.

• Access to emergency services will not be maintained for each closure. A paid duty police officer will be present during working hours to help control traffic flows at the intersection.

• Traffic delays are expected.

• Watch for slow moving vehicles entering and exiting work areas.

• Remember to reduce your speed when approaching lane reductions.

WHAT TO EXPECT?

• Every effort will be made to minimize disruptions.

• Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, triaxles, backhoes, and other construction equipment related to this work.

TRANSIT DETAILS

• MiWay will continue to operate with regular service.

• Watch for additional signs directing passengers at bus stops as boarding areas may be relocated.

• Visit www.miway.ca/updates for updates on your bus route.

PEDESTRIAN DETAILS

• Please take care when travelling near construction areas.

• Sidewalk access in the area could be affected.

• Watch for additional signs directing pedestrians as detours may be required.

• Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.

CONTACT US

• Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project.

24-hour line 416-202-7500.

Write to us at: peel@metrolinx.com
Find us on Twitter @HurontarioLRT
Visit the website and sign up for our newsletter: www.metrolinx.com/hurontariolrt

SCHEDULED WATER INTERRUPTION NOTICE – Watermain Replacement and Improvement 1541 and 1547 Hurontario Street – May 18

By Hurontario LRT, Resources, Ward 1

INTERRUPTION DETAILS

Date: Thursday May 18th, 2023

Time: 8:00 pm. to 6:00 a.m.

Location: 1541 and 1547 Hurontario Street Ward 1, City of Mississauga

Affecting: Approximately 1 Pharmacy and 3 Commercial Units affected

Project no.: 16-1390

Project Manager: Jay Christy

Telephone: (437) 339-3945

The Region of Peel Public Works department regularly maintains and repairs the water system to make sure you have a consistent supply of quality drinking water. Sometimes we must turn off your water supply while we do this work.

Your water will be turned off on Thursday May 18th, 2023, between 8 p.m. and 6 a.m. If we need to reschedule this work due to weather or other circumstances, we will let you know the new date and time.

Property owner/manager responsibilities during a water interruption

As a property owner/manager, it is your responsibility to:
•Ensure maintenance, mechanical or plumbing staff are on site during the water interruption, as it mayaffect internal systems that rely on water such as boilers, fire suppression, and alarms.
•Notify the fire alarm company if the interruption could affect an alarm system.
•Have a fire watch completed during the water interruption, as the building’s sprinkler protection systemwill not function when the water supply is shut off.

After the water interruption
When we turn the water back on, air in the pipes may make the water cloudy and your plumbing may vibrate or make noise. We recommend removing the air by slowly turning on your taps from the lowest to the highest faucet in the building (that is, starting in the basement/first floor, and finishing on the top floor). You will likely need to run the water for 10 to 30 seconds. Run the water until it is clear, and any vibration or noise has stopped.

Important note
After the water is turned back on, we recommend checking the water meter (usually located in the basement). If it is leaking, call Water Meter Installations Dispatch at:
•905-791-7800, extension 3226 (8:30 a.m. to 4:30 p.m. – Monday to Friday)
•905-791-7800 extension 4409 (after hours or statutory holidays)

Sign up for email notices
Receive timely project updates right to your inbox by signing up for e-notices at peelregion.ca/construction

Keeping you informed
We will let you know if there are any major changes to the plans.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water.
If you have any questions, please contact us.

Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409

LRT Construction Notice – New Water Service Connections to all Properties between Mineola Road to Pinetree Way

By Hurontario LRT, Ward 1

New Water Service Connections to all Properties between Mineola Road to Pinetree Way

May 3, 2023 to May 31, 2023 from 7 a.m. to 7 p.m.

What work is taking place?
As utility upgrades progress in the area, crews will be connecting all properties along Hurontario Street, between Mineola and Pinetree Way, to the new watermain infrastructure that has recently been installed along the road alignment. The work is expected to take place as early as May 3 and will last approximately one month to May 31. Crews will be working Monday to Saturday, starting at 7 a.m. each day. Some overnight work will be required at the direction of the Region of Peel for temporary water service disruptions during the connections.

All the connection points are within the municipal right of way. Most of the connection points are located within the municipal side of existing driveways or the public boulevard. To make these connections, crews will need to excavate a small area up to the property line. As a result, there may be temporary impacts to water service, driveway access, and lawns/trees/hedging that are in direct conflict with the connection points. All impacted driveways will be temporarily restored using hot mix asphalt until permanent restoration takes place with final grading and re-surfacing. Any disruption to lawns/trees/ hedging will be reinstated during the final landscaping phase of the project. Individual property owners/managers directly impacted will be notified by the Region of Peel in advance of the impacts specific to their water service connection.

All works will be carried out in accordance with the Ontario Municipalities Act for the purposes of providing a water public utility with respect to accessing private property as needed. For more information on this Act please visit the government of Ontario webpage on public utilities at https://www.ontario.ca/laws/statute/01m25#BK89

Please note, work may be rescheduled due to inclement weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.

TIMING
• Work is expected to begin as early as May 3, 2023, to May 31, 2023
• Working hours are Monday to Saturday, starting at 7 a.m. each day. Some overnight works will be required at the direction of the Region of Peel.
• Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.

TRAFFIC DETAILS
• Watch for slow moving vehicles entering and exiting work areas.
• Remember to reduce your speed when approaching lane reductions.

WHAT TO EXPECT?
• Every effort will be made to minimize disruptions.
• There may be temporary impacts to water service, driveway access, lawns/trees/hedging that are in direct conflict with the connection points.
• Individual property owners/manager directly impacted will be notified by the Region of Peel in advance of the impacts specific to their water service connection.
• Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators,
loaders, triaxles, backhoes, and other construction equipment related to this work.

TRANSIT DETAILS
• MiWay will continue to operate with regular service.
• Watch for additional signs directing passengers at bus stops as boarding areas may be relocated. Visit www.miway.ca/updates for updates on your route.

PEDESTRIAN DETAILS
• Please take care when travelling near construction areas.
• Sidewalk access in the area could be affected.
• Watch for additional signs directing pedestrians as detours may be required to ensure pedestrian safety.

CONTACT US
• Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project.
• 24-hour line 416-202-7500

UPDATE: Overnight and Weekend Work on the Lakeshore West Rail Corridor at Port Credit GO Station

By Hurontario LRT, Ward 1

May 2023 to July 2023 between the hours of 9 p.m. to 5 a.m

What work is taking place?

Construction crews will continue overnight activities within the railway corridor at Port Credit GO Station near Hurontario Street. These activities are expected to continue from May 2023 to July 2023 and will allow for grouting and excavation activities to continue while the underpass structure, also known as the Push Box, is pushed into place with minimal disruption to train movements overhead. Once in place, the underpass will allow for light rail vehicles to enter and exit Port Credit GO Station.
In order to complete the work safely and efficiently, crews will be onsite between the hours of 9 p.m. and 5 a.m. on weeknights when train movements are at a minimum. Some work may also be required on a few nights on the weekends.
We understand that we are building this transformational transit project in a residential area and that overnight work is not ideal. We appreciate your patience and will complete this work as efficiently as possible to get things back to normal for you. We have a dedicated community relations team in place to work with residents and businesses in Peel Region through the construction and operation of this transformational project.
Please note, work may be rescheduled due to weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.

TIMING

• Continuous overnight work will be scheduled between May 2023 to July 2023. • Overnight work will occur overnight between 9 p.m. to 5 a.m. when train movements are at a minimum. Impacts are dependent upon the specific activities being performed and not every night will be noisy. • Nighttime works may be scheduled during weekend nights. • Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.

TRAFFIC DETAILS

• This work is localized in the southeast portion of the Port Credit parking lot, directly adjacent to the railway corridor. • Traffic delays are expected where lane reductions already exist for utility and roadwork activities on Hurontario Street. There are no additional traffic impacts related to this work. • Watch for slow moving vehicles entering and exiting work areas. • Remember to reduce your speed when approaching lane reductions.

WHAT TO EXPECT?

• Every effort will be made to minimize disruptions. • Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, tri-axles, backhoes, and other construction equipment related to this work.

PEDESTRIAN DETAILS

• Please take care when travelling near construction areas. • Sidewalk access in the area could be affected. • Watch for additional signs directing pedestrians as detours may be required. • Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.

CONTACT US

• Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project. • 24-hour line 416-202-7500.

Contact Us:
Call us: 416-202-7500
Write to us at: peel@metrolinx.com
Find us on Twitter @HurontarioLRT
Visit the website and sign up for our newsletter: www.metrolinx.com/hurontariolrt

Road Closure at Harborn Road and Hurontario Street

By Hurontario LRT, Ward 1

Friday May 5 at 7 p.m. to Monday May 8, 2023 at 6 a.m.
Works are scheduled to take place 24 hours a day

What work is taking place?
Construction crews will be installing new watermain and stormwater pipes along Hurontario Street and Harborn Road, resulting in a temporary closure of a portion of Harborn Road. This closure is scheduled to begin May 5, 2023 at 7p.m to May 8, 2023 at 6a.m. Works are scheduled to take place 24 hours a day to ensure work can be completed safely and efficiently. Emergency access will be maintained.
In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, and other construction equipment related to this work.
Please note, work may be rescheduled due to weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com and our team will provide you with e-updates of this work.

TIMING
• A portion of Harborn will be closed from May 5 at 7p.m., 2023 to May 8, 2023, at 6a.m.
• Works are scheduled to take place 24 hours a day.
• Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.
TRAFFIC DETAILS
• Access to Harborn Road will be maintained through a detour from Hurontario Street, The Queensway, Stavebank Road and Premium Way.
• Emergency access will be maintained.
• Watch for slow moving vehicles entering and exiting work areas.
• Remember to reduce your speed when approaching work zones.
WHAT TO EXPECT?
• Every effort will be made to minimize disruptions.
• Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, tri-axles, backhoes, and other construction equipment related to this work.
TRANSIT DETAILS
• MiWay near the intersection will continue to operate with regular service.
• Watch for additional signs directing passengers at bus stop as boarding areas may be located.
• Visit www.miway.ca/updates for updates on your bus route.
PEDESTRIAN DETAILS
• Please take care when travelling near construction areas.
• Watch for additional signs directing pedestrians as detours may be required.
• Clear and defined walking paths will be maintained during construction to ensure pedestrian safety
CONTACT US
• Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project.
• 24-hour line 416-202-7500

Contact Us:
Call us: 416-202-7500
Write to us at: peel@metrolinx.com
Find us on Twitter @HurontarioLRT
Visit the website and sign up for our newsletter: www.metrolinx.com/hurontariolrt

Hurontario LRT Construction Notice

By Hurontario LRT, Issues, Ward 1

Hurontario LRT Construction Notice
Information as of: March 2023
Temporary Road Closure of
Mineola Road West at Hurontario
Street for Stormwater Installation
Saturday April 15 from 7 a.m. to 10 p.m.
Contact Us:
Call us: 416-202-7500
Write to us at: peel@metrolinx.com
Find us on Twitter @HurontarioLRT
Visit the website and sign up for our newsletter: www.metrolinx.com/hurontariolrt
What work is taking place? As utility upgrades progress in the area, crews will be installing stormwater infrastructure along the west side of Hurontario Street at Mineola Drive West. The working hours will take place on Saturday April 15 from 7 a.m. to 10 p.m. This will involve the full closure of Mineola on the west side of Hurontario Street to accommodate the storm crossing. Work is being scheduled to minimize traffic and overnight noise impacts to nearby residents.
In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, loaders, and other construction equipment related to this work.
Please note, work may be rescheduled due to inclement weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.
TIMING • Work is scheduled for April 15, 2023, from 7 a.m. to 10 p.m. • Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.
TRAFFIC DETAILS • Temporary lane reductions will be required on Hurontario Street. • Access to Mineola Road West from Hurontario Street will be available from Indian Valley Trail and Glenburnie Road. • A paid duty police officer will be present during working hours to help control traffic flows at the intersection. • Traffic delays are expected. • Watch for slow moving vehicles entering and exiting work areas. • Remember to reduce your speed when approaching lane reductions.
WHAT TO EXPECT? • Every effort will be made to minimize disruptions. • Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators,
loaders, triaxles, backhoes, and other construction equipment related to this work.
TRANSIT DETAILS • MiWay will continue to operate with regular service. • Watch for additional signs directing passengers at bus stops as boarding areas may be relocated. • Visit www.miway.ca/updates for updates on your bus route.
PEDESTRIAN DETAILS • Please take care when travelling near construction areas. • Sidewalk access in the area could be affected. • Watch for additional signs directing pedestrians as detours may be required. • Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.
CONTACT US • Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project. • 24-hour line 416-202-7500.