Tuesday August 23 to Tuesday August 30, 2022, 24-hour works Read More
TEMPORARY ROAD CLOSURE
MINEOLA ROAD WEST AT HURONTARIO STREET
HuLRT UTILITY INSTALLATION
The contractor is installing underground utilities at Hurontario Street and Mineola Road West. Due to the underground conditions, the duration of the temporary closure must be further extended. During the closure, no vehicles (including Emergency Services) will be able to access Mineola Road West from Hurontario Street. The signed detour uses Indian Valley Trail and Glenburnie Road to access Mineola Road West.
Variable Message Signs have been updated to advise motorists of the extended closure of Mineola Road West.
Mineola Road West at Hurontario – Temporary Road Closure Update
- From now through to Saturday August 20th at 10:00 pm the constructor will continue to work 24 hours a day.
Should you have any questions or concerns, please contact the undersigned.
NOTE: Construction schedules are subject to change due to weather conditions and unforeseen construction conditions. Should the schedule require changes for any reason, an updated notice will be circulated.
In preparation for the construction of the Hurontario LRT, the constructor must close Pinewood Trail just east of Hurontario Street to install an electrical duct bank.
During the closure, no vehicles (including Emergency Services) will be able to access Pinewood Trail from Hurontario Street. A signed detour will be erected that uses Mineola Road East and Goldthorpe Road to access Pinewood Trail.
Variable Message Signs will been installed to advise motorists of the planned closure and a copy of the notification letter that was hand delivered to residents in the area is attached.
The road closure will take place:
- Tuesday August 16th, 2022 at 7 am through to Saturday August 20th at 5:00 pm. Work will be occurring 24 hours a day.
NOTE: Construction schedules are subject to change due to weather conditions and unforeseen construction conditions. Should the schedule require changes for any reason, an updated notice will be circulated.
What work is taking place?
Construction crews will be installing utilities along Hurontario Street that will also need to cross Pinewood Trail. This will result in a temporary closure of a portion Pinewood Trail from 7 a.m on August 16 to 5 p.m. on August 20, 2022. The road closure and construction will be continuous throughout this duration.
In accordance with City of Mississauga Noise By-Law Exemption requirements, this notice is meant to advise that residents near the work site can expect to hear noise and vibration caused by trucks, excavators, backhoes, and other construction equipment related to this work. Some of this work will be done overnight and, on the weekend, so crews will be able to complete this work safely and efficiently.
During this closure, motorists can access Pinewood Trail from Hurontario Street using the detour map provided. Please note, work may be rescheduled due to weather or unforeseen circumstances. If you require the most up-to-date information, please reach out to peel@metrolinx.com.
TIMING
Pinewood Trail will be closed from: o 7 a.m. August 16 to 5 p.m. August 20, 2022 o The road closure and construction work will be continuous throughout this duration
Work could be rescheduled and delayed due to weather conditions or unforeseen circumstances.
TRAFFIC DETAILS
Access to Pinewood Trail will be maintained through a detour from Hurontario Street, Mineola Road East and Goldthorpe Road.
Watch for slow moving vehicles entering and exiting work areas.
Remember to reduce your speed when approaching work zones.
WHAT TO EXPECT?
Every effort will be made to minimize disruptions.
Residents and businesses near the work site can expect to hear noise and vibration caused by trucks, excavators, loaders, triaxles, backhoes, and other construction equipment related to this work.
TRANSIT DETAILS
MiWay near the intersection will continue to operate with regular service.
Visit www.miway.ca/updates for updates.
Watch for additional signs directing passengers at bus stop as boarding areas may be relocated.
PEDESTRIAN DETAILS
Please take care when travelling near construction areas.
Watch for additional signs directing pedestrians as detours may be required.
Clear and defined walking paths will be maintained during construction to ensure pedestrian safety
CONTACT US
Metrolinx has a dedicated community relations team in place to work with residents in Peel region through the construction and operation of this transformational transit project.
24-hour line 416-202-7500.
Stop(s) Impacted: No.: 0333: SB Hurontario St at Mineola Rd W
Temporary Stop Location: Temporary marker to be placed 20m to the South
Routes Impacted: 2 South
Date and Time: Effective Immediately
Estimated Duration: until Friday, August 26, 2022 @ 5:00pm
Event Type: HuLRT
Agency: Mobilinx
Notes:
– Stops will remain accessible;
– No detours required.
Please be advised that the above will be filming interior scenes for a “Natalist” commercial at 1649 Sunnycove Dr (Ward 1) on August 12th, 7:00 AM – 11:00 PM. Any prep and wrap activity will be entirely on private property.
A permit has been granted to allow parking on the following:
- One side of Sunnycove Dr between Laughton Ave and Tarn Rd
August 10, 2022
A Region of Peel delegation consisting of the Regional Chair and members of Regional Council will be attending the 2022 Association of Municipalities of Ontario (AMO) conference, August 14-17 in Ottawa. The Region participates annually in this AMO’s premier event, which provides Ontario municipalities with a forum for conversation with provincial decision-makers regarding ongoing challenges and with opportunities for collaboration and learning through numerous workshops and information sessions. Read More